Hyderabad: After laying foundation for the works on the country's first bullet train between Ahmedabad and Mumbai recently, the Indian Railways has signed a joint declaration of intent with German Railways to carry out feasibility study on existing Chennai-Kazipet corridor for increasing the speed trains to 200kmph.
At present, the travel time between Chennai and Kazipet in Telengana, a distance of around 643kms, is around 11 hours. If the semi-high speed corridor is developed, the distance will be covered in 3 hours 15 minutes.
The Project is envisaged to consist of three phases to be carried out over a 22-month period with the objectives to provide:
Phase 1: Definition of three demand-based upgrade scenarios for the corridor
Phase 2: Selection of the preferred upgrade scenario for SHS on the corridor, based on analysis of respective operations and economic-financial impact
Phase 3: For preferred scenario, Reference design and technical Tender document
The cost of the feasibility study will be shared in 50:50 ratio by the Ministry of Railways and the German government.
Salient features of Chennai-Kazipet corridor:
Route: Chennai-Gudur Jn-Nellore-Tenali Jn-Vijayawada Jn-Warangal-Kazipet Jn Total length of the corridor – 643 km (135km in Southern Railway and 508km in South Central Railway) and the entire corridor is electrified.